Land Survey and GIS

All the most necessarily in Land Surveying

Land Survey and GIS

All the most necessarily in Land Surveying

Topographic Survey Requirements

Sanitary Sewer Overflow (SSO) Control

and Wastewater Facilities Program

Topographic Survey

Requirements

City of Baton Rouge/Parish of East Baton Rouge

Department of Public Works

Submitted by

Prepared by: Tim Jett

Reviewed by: Jennifer Baldwin

Approved by: James Hawley

Revision 1

August 2009


MKE/092380086 III REV. 1 / AUGUST 2009

Contents

Section Page

1. Introduction........................................................................................................................1-1

2. General ................................................................................................................................2-1

3. Control Points .....................................................................................................................3-1

4. Survey Limits and Cross Sections...................................................................................4-1

5. Utility Locations .................................................................................................................5-1

6. Deliverables........................................................................................................................6-1


MKE/092380086 1-1 REV. 1 / AUGUST 2009

1. Introduction

This document provides requirements for surveying performed for projects associated with

the City of Baton Rouge/Parish of East Baton Rouge (C-P) Sanitary Sewer Overflow (SSO)

Control and Wastewater Facilities Program. The term Engineer is defined as an engineering

design firm under contract with the C-P and producing engineering design work on the

Program. These requirements are provided to encourage consistency in the design approach

used by various Engineers.

While the purpose of these requirements is to assure uniformity, it is not intended to stifle

Engineer’s creativity, design innovation, and ingenuity. Engineers shall review these

requirements and adopt them for design of the facilities for which they are responsible.

Engineers are ultimately responsible for their design, and this responsibility is in no way

diluted or absolved by these requirements.

It may be necessary for the Engineer to deviate from these requirements. In such cases, the

Engineer shall immediately bring this matter to the attention of the Program Manager (PM)

by completing and submitting the form included in the Program Requirements for Engineers.

The PM reserves the right to allow or disallow the deviation from the requirements. If the

deviation will impact design contract terms, then a Supplemental Agreement will be

negotiated between the Engineer, the PM, and the C-P.


MKE/092380086 2-1 REV. 1 / AUGUST 2009

2. General

The surveyor shall follow the current standards of practice as outlined in the Laws and

Rules of the Louisiana Professional Engineering and Land Survey Board in conducting

surveys. As such, all work shall adhere to modern surveying theory, practice, and

procedures. Surveys shall be performed in English units and all data collected shall be

reduced to state plane coordinates.

If right-of-way or servitude maps are required for the project, they shall be prepared in

accordance with the Program Right-of-Way Map/Real Estate Standards.


MKE/092380086 3-1 REV. 1 / AUGUST 2009

3. Control Points

Horizontal and vertical control points for design, topographic, boundary, and construction

surveys shall meet the accuracy of surveys for a Class A (Urban) Survey as outlined in the

Rules of the Louisiana Professional Engineering and Land Survey Board. Horizontal control

shall be NAD 83 (92) and vertical control shall be NAVD 88. Surveyor shall only use EBR 88

monuments.

As part of the C-P SSO Program, the C-P Department of Public Works (DPW), in

conjunction with the U. S. Army Corps of Engineers, New Orleans District, has established

20 vertical control benchmarks to be utilized for surveying performed as part of the

Program. Information related to these benchmarks including their locations is available on

the Program Web site at www.brprojects.com/sewer/pages/contractor_guidelines.htm.


MKE/092380086 4-1 REV. 1 / AUGUST 2009

4. Survey Limits and Cross Sections

The Engineer shall perform survey work to determine all surface features and at or below

ground elevations at the project site and/or located within the right-of-way along the entire

alignment and other areas as may be necessary to develop plan and profiles and site plans

for the recommended project. The Engineer may choose to utilize Global Positioning System

(GPS) data for mapping of x-y coordinates. The scope of the surveying work shall include,

but not be limited to:

• Determining boundary conditions (site property boundary, temporary and permanent

servitude widths determined, and rights-of-way-widths).

• Confirming existing facilities controls and elevations with current survey and

Establishing additional survey control points where required.

• Identifying mapping options and develop preliminary and/or final design mapping.

• Performing field survey in State Plane Coordinate control. All existing surface features

within the project limits shall be shown. Surface features include, but are not limited to,

edge of pavement, pavement type, curb, gutter, sidewalks, retaining walls, driveways,

parking lots, utility poles, utility towers, overhead electric lines, pavement markings

(including type of pavement marking), traffic lights, traffic signs, all other signs, tree

type and trunk diameter, drainage channels (including invert and water surface

elevations at sewer line crossing), water bodies (ditches, streams, creeks, rivers, ponds,

etc.) including invert and water surface elevations at sewer line crossing, railroads,

structures, bridges, columns, telephone boxes, fences, gates, and all other surface

features. The size and type of all surface features shall be shown.

• Performing phased or final design level mapping.

• Defining legal issues and constraints (ownership’s, zoning, servitudes, etc.).

• Obtaining parcel maps and ownership information within the project limits. Property

corner surveys shall be conducted within the project limits. All existing lot numbers and

plat information shall be shown.

• Field surveying pavement match points (curbs, gutter, sidewalk, pavements, etc.).

• Researching and showing records of existing adjacent public utility systems.

• Plotting all existing utilities (see Louisiana R.S. 38:2223).

• Field surveying and showing on drawings all underground features and utilities within

the project limits. These include, but are not limited to, sanitary and storm sewers,

water, gas, electric, telephone, cable, fiber optic, traffic loops, services (water, sewer, gas,

and all other services), manholes (including top and invert elevation), utility vaults

(including top and invert elevation), valve boxes (water valves, sewer valves, gas valves,

and all other valves, including top and invert elevations), storm inlets (including top and

TOPOGRAPHIC SURVEY REQUIREMENTS

REV. 1 / AUGUST 2009 MKE/092380086

invert elevation), junction boxes (including top and invert elevation), utility

appurtenances, cleanouts, water meters, lift stations (wet wells, dry wells, and aboveground

piping and valves, including top and invert elevations for wet wells and dry

wells and surface drains and centerline elevations for above-ground piping and valves),

septic systems, storage tanks, and all other underground features. The type, size,

alignment, depth, and top and invert elevations of the underground features shall be

noted. Slopes and flow lines shall be noted for existing sewer lines. Materials of

construction of underground utilities shall be provided where available.

• Survey existing building floor elevations at all identified pump station sites. Provide one

XYZ coordinate on flat open ground in the immediate vicinity of each of the identified

existing and proposed pump stations.

If applicable, special areas or elements to be mapped (using GPS data) include:

• Hazardous materials

• Archaeologically important areas

• Wetlands/endangered species

• Flood plains

• Geotechnical exploration drill holes and test pits

MKE/092380086 5-1 REV. 1 / AUGUST 2009

5. Utility Locations

The Engineer shall collect as-built utility drawings and utility inventory from the Program

Manager. The surveyor shall collect all visible utilities and utility markers and show them

on the survey plans. The surveyor shall also call LA One Call and collect location of the

underground utilities as indicated by LA One Call. Surveyor shall submit call or reference

number received from LA One Call to the Program Manager as verification of the request

for utility locations. If additional utility location activities are included in the Project scope,

such as potholing, the surveyor will also include the locations of all utilities located by these

additional activities on the survey plans and profiles, as applicable.


MKE/092380086 6-1 REV. 1 / AUGUST 2009

6. Deliverables

The survey shall include the following deliverables, to be submitted with other design

deliverables, as appropriate.

• Copy of all survey notes and field roll

• Plan and profiles broken into 24 x 36-inch sheets with station and offset to all utility

poles, fire hydrants, building corners, headwalls, and drainage structures

• Vertical profiles showing the existing centerline ground surface above the proposed pipe

or structure, drainage pipes, pipeline crossings, utilities, ditch centerlines, and other

critical information

• AutoCAD drawings, in accordance with the Program CAD Requirements, showing all

collected data in three dimensional coordinates along with the required pen setting files

• Drawing files in pdf format at full size (24 x 36)

نظرات 0 + ارسال نظر
امکان ثبت نظر جدید برای این مطلب وجود ندارد.